Following the perennial power outages currently being experienced across the country; findings have shown that 20 gas power plants are currently under-performing, leading to power generation dropping below 2,000MW.

Nigeria has 23 power generating plants with 11,165MW capacity connected to the national grid. These plants are managed by generation companies (GenCos), independent power providers, and Niger Delta Holding Company. Out of the 23, two are hydro plants.

Independent investigations by The PUNCH showed that the gas plants are currently either generating below expectations, shut down due to lack of gas, or undergoing maintenance.

Investigations further showed that the affected plants included: Omotosho units 5 & 6, Olorunsogo units 3, 4 & 6, Omoku Units 3 & 6, Omotosho NIPP units 3 & 4, Delta units 15, 17, and 18, Afam VI units 11 & 12, Olorunsogo NIPP unit 3, Ihovbor NIPP unit 2, Sapele Steam unit 3, Sapele NIPP unit 1, Odukpani NIPP units 1 & 3, and Okpai units 11, 12 & 18.

Also, Jebba Hydro and Shiroro power generating stations are either out or have limited generation capacity.

Other affected power generating plants include: Omotosho units 3&4, Olorunsogo unit 1, Delta units 10 &20, Afam VI unit 13, Ihovbor NIPP unit 4, Geregu NIPP units 22&23 and Odukpani NIPP units 2, 4 & 5. These are out either because of fault or for scheduled maintenance.

The two hydro plants, Shiroro and Jebba, are also experiencing generation shortfall due to water management.

Further checks revealed that there were fault and technical problems in the country’s largest gas plant, Egbin, which took it completely off the grid, causing 514MW shortfall. 

In Geregu, the situation caused 230MW shortfall, with reported fault at Alaoji NIPP. Olorunsogo, Omotosho, Sapele NIPP, Omotosho NIPP, Omoku, Okpai, Afam VI, Olorunsogo NIPP, Geregu NIPP, and Ihovbor are also experiencing different constraints currently weighing down their performances.

Odukpani NIPP, which was recently shut down due to gas pipeline pigging, is also yet to fully bounce back to full generation capacity.

However, 16 gas plants were on weekend back on the national grid with Delta Power generating the highest at 332MW.

Also on the grid are: Rivers IPP (160MW), Sapele (53MW), Sapele NIPP (94.90MW), and Shiroro Hydro (122MW).

Power generation was put at 1,936.90 mega watts from 3,647MW last recorded.

Ministry of Power over the weekend confirmed The PUNCH findings when it released a statement apologising to the public over the current dip and stated that there was a partial shutdown of the Oben gas plant to address the repair of critical gas processing equipment.

“The incident, unfortunately, occurred at a time when other power plants on other gas sources are undergoing planned maintenance and capacity testing,” the statement signed by Special Adviser to the Minister of Power, Isa Sanusi, said.

Spokesperson for Eko Electricity Distribution Company, EKEDC, Godwin Idemudia, said the station currently got low allocation from the Transmission Company of Nigeria.

According to Idemudia, as of Saturday, load allocated to it was a mere 240MW out of expected 861MW.

“This affects all our injection substations. For example, Alangbon TS (covers IKoyi, Keffi, Obalende and environs) is expected to be 135 mw but we got 64.4 mega watts. On the overall, instead of getting 861mw, we are given 240.1 mw. We cannot give what we don’t have. The only way out is to load shed so it can go round all our customers,” he said.

The TCN had blamed the situation on a combination of issues ranging from gas constraints, fault, and technical problems within generating plants which caused persistent low generation and consequently low load allocation to distribution companies nationwide.

“This is based on the fact that TCN can only transmit what is being generated by Gencos and presently they are all generating below capacity,” the transmission company stated in a note.

 

Punch

June 26, 2025

How to ace a job interview in 90 seconds, from an Ivy League communication expert

Sophie Caldwell You only have about 90 seconds to make a strong first impression in…
June 26, 2025

Peter Obi decries ‘coordinated lawlessness’ after brother’s property is demolished in Lagos without court order

Former presidential candidate Peter Obi has condemned what he described as a brazen act of…
June 27, 2025

Which drink is best for hydration? Hint: It isn’t water

Lisa Drayer When you’re thirsty and in need of a drink, which beverages are best…
June 21, 2025

Man convicted of posing as flight attendant to fly for free 120 times

A 35-year-old American man has been found guilty of impersonating a flight attendant at least…
June 26, 2025

17 soldiers killed, dozens injured in fierce gun battles with terrorists in Niger, Kaduna

Seventeen soldiers have been confirmed dead and at least ten others injured following coordinated attacks…
June 27, 2025

What to know after Day 1219 of Russia-Ukraine war

WESTERN PERSPECTIVE Russia captures village in eastern Ukraine near lithium deposit, Russian-backed official says Russian…
June 25, 2025

Tesla robotaxi launch: Why getting from dozens to millions of self-driving cars won't be easy

Tesla (TSLA.O) finally has a robotaxi. Now comes the hard part. The electric-vehicle maker deployed…
May 13, 2025

Nigeria's Flying Eagles qualify for World Cup after dramatic win over Senegal

Nigeria's U-20 national football team, the Flying Eagles, have secured their place at the 2025…

NEWSSCROLL TEAM: 'Sina Kawonise: Publisher/Editor-in-Chief; Afolabi Ajibola: IT Manager;
Contact Us: [email protected] Tel/WhatsApp: +234 811 395 4049

Copyright © 2015 - 2025 NewsScroll. All rights reserved.