Sunday, 15 January 2017 03:03

Fresh row over new N7b VP’s residence

Rate this item
(0 votes)

With about N6.215billion already spent in eight years on the new official residence of the nation’s Vice President in Abuja, the project remains enmeshed in controversy.

While the House of Representatives Committee on FCT is alleging that the job done is not commensurate with the 87 percent of the contract sum paid, no one seems to know when the project will be ready for occupation.

The project has been abandoned in the last five years owing to disagreement between the Senate and the Federal Capital Development Authority on the variation of the project.

The contract was awarded in 2009 at a cost of N7billion but N6.215 billion was paid to the contractors.

In 2012, immediate past Minister of the FCT, Senator Bala Mohammed, submitted a request for additional N9billion to complete the project.

Although the Bureau of Public Procurement (BPP) scaled down the variation cost to N6billion, the 7th Senate rejected it following an intelligence report that “the request for the additional cost was suspicious.”

The complex is made up of the followings: VP’s ADC’s house (N258m); Chief Security Officer’s house (N228m); mosque (N95m); Church (N84m); security quarters, (N114 m); boys quarters (N288m); Gate House (N55m); infrastructure (N1.7 billion), among others.

While the government was trying to find solution to the contract stalemate, a fresh row is trailing the new residence.

The row borders on:

• Suspected inflation of the cost

• Job done allegedly not commensurate to the 87 percent payment of the contract sum

• Why did the construction company only ensure 50 per cent completion of project after 87 per cent payment

• Alleged outrageous request for variation of the project

*Lack of timeframe for the completion of the residence

Chairman of the House Committee on FCT, Hon. Herman Hembe, who spoke with one of our correspondents yesterday, said his committee was disappointed at the way the contract was being managed.

Hembe said: “In all, about 87 percent of the contract sum has been paid. You can go and take a look and see for yourself if the work done is commensurate with the funds so far paid.

“The committee has severally expressed disappointment over this very sad situation.”

A top source said: “We are suspecting underhand dealings by some key officials in the past administration of ex-President Goodluck Jonathan.

“Initially, a variation of N13billion was proposed but public outcry forced them to reduce it to N9billion before the BPP scaled it down to N6billion.

“Also, the job done is about 50 percent but 87 percent payment of the contract sum was effected.

“As I am talking to you, nobody knows the timeframe for the completion of the project. And when the 87 percent payment was done, the agreement included furnishing materials. But we learnt the contract scope has been altered.

“Already there is provision for the project in 2017 budget but the administration of President Muhammadu Buhari should take more than a passing interest in the residence. The project is being turned into a goldmine by some officials. Let there be a comprehensive audit of the extent of work in line with the contract terms.”

Another source said: “There is a dilemma on what to do because the residence is not a priority project for this administration. The nation cannot afford to spend as much as additional N6billion on the new residence.

“Again, the government cannot abandon the project after attaining about 50 percent completion. But the resources are not just there now. The only option is the completion of the project in phases.

Responding to a question, the source added: “The nation has about 19,000 projects abandoned in the last 42 to 43 years. We may need about N12trillion to complete these projects, including the new residence of the Vice President.

“Some people are even suggesting that the project should be converted to either a hospital or an office space for any of the security agencies.”

All calls and text messages sent to the Special Assistant to the FCT Minister on Media, Sani Abubakar, and Chief Press Secretary, Muhammad Sule, were not acknowledged.

 

The Nation 

December 20, 2024

Naira expected to weaken further, says CBN business survey

Nigerian businesses anticipate further depreciation of the naira through early 2025, despite maintaining overall optimism…
December 20, 2024

Atiku questions alleged hack of NBS website, says timing suspicious

Former Vice President Atiku Abubakar has raised concerns over the recent claim that the website…
December 22, 2024

How to know if your memory lapses are serious or not

The older I get, the more panicked I become when something slips my mind. Is…
December 21, 2024

‘Professional Back-Scratchers’ charge up to $130 per hour

The Scratcher Girls is an unconventional relaxation therapy studio that charges clients up to $130…
December 21, 2024

NAFDAC busts illegal rice repackaging operations in Nasarawa, Abuja

The National Agency for Food and Drug Administration and Control (NAFDAC) has cracked down on…
December 22, 2024

Here’s the latest as Israel-Hamas war enters Day 443

Israel and Hamas appear close to a ceasefire deal. These are the sticking points Israel…
December 20, 2024

OpenAI launches voice and text access to ChatGPT through new phone service

OpenAI has introduced a novel way to interact with its popular ChatGPT artificial intelligence system…
December 17, 2024

Ademola Lookman named 2024 CAF Men’s Player of the year. These players won in other…

Ademola Lookman, the Super Eagles winger, was crowned the 2024 CAF Men’s Player of the…

NEWSSCROLL TEAM: 'Sina Kawonise: Publisher/Editor-in-Chief; Prof Wale Are Olaitan: Editorial Consultant; Femi Kawonise: Head, Production & Administration; Afolabi Ajibola: IT Manager;
Contact Us: [email protected] Tel/WhatsApp: +234 811 395 4049

Copyright © 2015 - 2024 NewsScroll. All rights reserved.